AFTERBAY RESERVOIR
• Disturbed Area: 395-acres
• Upper-Level Liquid Area: 7,976,947-ft2 (183-acres)
• Bottom-Level Liquid Area: 5,019,662-ft2 (115-acres)
• Liquid Depth: 143-ft, Freeboard: 7.0-ft (Above Upper Liquid Level)
• Average (50% of Volume) Liquid Depth: 80-ft
• Liquid Storage: 22,235 acre-ft
• Dam Type: Rockfill (Balanced Cut & Fill),Spillway: To Be Determined
• Annual Evaporation: 323 acre-feet with covers
• Rain/Snow Catchment Area: 3,100-acres, Annual Moisture: 1,500 acre-feet
FOREBAY RESERVOIR
• Disturbed Area: 327-acres
• Top-Level Liquid Area: 12,513,122-ft2 (287-acres)
• Bottom-Level Liquid Area: 2,574,835-ft2 (59-acres)
• Average (50% of Volume) Liquid Depth: 75-ft
• Liquid Depth: 133-ft, Freeboard: 7.0-ft (Above Upper Liquid Level)
• Liquid Storage: 22,235 acre-ft
• Dam Type: Rockfill (Balanced Cut & Fill), Spillway: To Be Determined
• Annual Evaporation: 988 acre-feet
• Rain/Snow Catchment Area: 1,000-acres, Annual Moisture: 500 acre-feet
RESERVOIR HEAD DATA
• Average Static Head: 2,275-feet
• Maximum Falling Head: 2,413-feet
• Minimum Falling head: 2,137-feet
POWERHOUSE, FLOWS and EQUIPMENT
• Conventional Francis Turbines with single speed pumps with synchronized
Motor/Generators
• No. Powerhouses: 3
• Total No. Turbine/Pump Units: 9 (3-Units per Powerhouse)
• Water Flow per Turbine/Pump Unit: 777,819-gpm, All Turbines: 7,000,372-gpm
• Maximum Power Output: 3-GW
• Maximum Duration (Based on Reservoir): 12-hrs
• Annual Power Generation: 12-hr. Periods: 13,140-GWh, 10-hr. Periods: 10,950-GWh
• Pump Cycle Efficiency: 87.2%
• Turbine Cycle Efficiency: 88.7%
• Round Trip Efficiency (RTE) with losses and Leakage: 77.2%
• Motor/Generator Units: 382-MW
UNDERGROUND EXCAVATIONS
• Access Tunnel Network: 25,800-ft
• Tailrace Discharge Branches: 24,422-ft
• Powerhouse Tailraces, Penstocks, Accesses: 6,578-ft
• Intake Shafts: 2 x 2,535’
• Discharge Shafts: 2 x 135’
• Secondary Ventilation/Access Shaft: 2,100-ft.
ELECTRICAL and TRANSMISSION
• Generator output underground 23kV, increased to 500kv at an underground substation
• Surface substation will reduce to a 500kV OH line and a 345kV OH line
• Each line is 6.2-miles in length
• 2,250MW will be delivered via the 500kV OH line, 750MW via the 345kV OH line
• Both high voltage lines will deliver to the connection with a VD of less than 2-percent
• Generators Power Factor: 83.2% Lagging
MISCELLANEOUS
• Required road upgrade/rehabilitation Forebay: 12-miles
• Required new road construction Forebay: 1.9-miles (plus 4-miles in site roads)
• Required new road construction Afterbay: 3.5-miles (plus 3-miles in site roads)
• Water well development: Red Lake, 6.7-mile pipeline to site
• Project located on: BLM land, project area 5,373-acres (1/8 section rule, includes roads)
• Makeup water pumping requirements is 1,400-gpm for 20-hrs/day
FERC Preliminary Permit Awarded on Oct 15 2024
You can see and download our full PowerPoint presentation by using the button below.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.